The QA workflow covers the final verification phase where the QA team validates completed development work and transitions specifications from under-test to released status. This process ensures that only properly verified features reach end users.

Overview

When development work reaches the under-test status, the QA team takes ownership of the validation process. After successful verification against acceptance criteria and test scenarios, the team transitions the specification to released status.

under-test  ──>  released

If testing fails, the work returns to an earlier status for correction.

Workflow Stages

Under-Test (Starting Point)

The development team has signaled that implementation is complete and the specification is ready for verification.

What the QA team receives:

  • A specification with clearly defined acceptance criteria
  • Implementation that the development team considers complete
  • Full traceability from the specification back to business goals
  • Visibility into what changed compared to previous versions

Testing in Progress

The QA team conducts validation activities.

Who owns it: QA team

What happens:

  • QA team members review the specification's acceptance criteria
  • Testing is performed against the implemented functionality
  • Test results are recorded
  • Issues found are documented and communicated

What QA team members can do:

  • View all work items currently in under-test status
  • Access the details of work items they need to test
  • Indicate when testing has passed or failed
  • Transition items to released when validation is complete

Released (Transition Target)

The specification has been verified and is available to end users.

Who performs the transition: Authorized QA team member

What this signals:

  • All acceptance criteria have been verified
  • The implementation meets the specification requirements
  • The feature is approved for production use

Key rules:

  • Only users with QA team authorization can transition items to released
  • Work items must be in under-test status before they can be released
  • The release transition must capture an audit trail of who approved the release
  • Work items cannot skip the under-test phase

Test Failure

When testing reveals issues that need correction.

What happens:

  • The QA team member indicates the test failure
  • The work item returns to an earlier status for rework
  • The development team addresses the issues
  • The item returns to under-test for re-verification

Transition Criteria

From To Requirements
under-test released All acceptance criteria verified; authorized QA team member approves
under-test (earlier status) Test failure documented; returned for rework

QA Team Responsibilities

  1. Review acceptance criteria -- understand exactly what needs to be verified
  2. Validate implementation -- test against the specification, not assumptions
  3. Document results -- record what was tested and the outcome
  4. Approve or reject -- make a clear decision on each work item
  5. Maintain the audit trail -- every decision should be traceable

Status History

Every QA transition is recorded with:

  • The QA team member who performed the action
  • A timestamp of the decision
  • Whether the item was released or returned for rework
  • Context or notes about the decision

Tips for QA Teams

  1. Start with the acceptance criteria -- they define the pass/fail boundaries
  2. Check the specification hierarchy -- understand the feature's context within goals
  3. Verify traceability -- ensure tests map back to acceptance criteria
  4. Communicate clearly when returning items for rework -- the development team needs to understand what failed
  5. Use the SPECLAN tree view to quickly see all items awaiting testing